A flexible-budget variance is $800 favorable for unit-related costs. This indicates that
a. costs were $800 more than the master budget
b. costs were $800 less than for the planned level of activity
c. costs were $800 more than standard for the achieved level of activity
d. costs were $800 less than standard for the achieved level of activity