To complete the first setup on a new machine took an employee 200 minutes

ACCOUNTING

Multiple Choice

To complete the first setup on a new machine took an employee 200 minutes. Using an 80% cumulative average-time learning curve indicates that the second setup on the new machine is expected to take

a. 160 minutes.

b. 120 minutes.

c. 80 minutes.

d. 60 minutes.